Detailed Project Reports:

Highways & Expressways

Construction of Mumbai - Pune Expressway, Kon to Kalamboli bypassing Panvel town Package-I.

  •  Length: 8.10 kms
  • Configuration: 6 lane Expressway
  • Project Cost: Rs. 90 Crs.
  • Client: Maharashtra State Road Development Corporation Ltd., Mumbai
  • Other Features if any: India’s first six-lane concrete, high-speed, access controlled expressway.

Four Laning of Satara - Kolhapur up to Maharashtra State Border, Section of NH-4, Package-II from Km 616/000 to Km 639/000.

  • Length: 23 kms (includes 2 Flyovers & 2 Major River Bridges)
  • Configuration: 4 lane
  • Project Cost: Rs. 112 Crs.
  • Client: Maharashtra State Road Development Corporation Ltd., Mumbai
  • Other Features if any: The project was part of Golden Quadrilateral Delhi – Kolkata – Chennai – Mumbai

DPR for Renewal / Strengthening of 4 lanned Road, Balance work of widening of 2 lane to 4 lane of Manor-Wada (SH-34) from Km 29/550 to 53/800 & Wada – Bhiwandi (SH-35) from Km 49/000 to 89/070 & Construction of Bhiwandi Bypass in the State of Maharashtra.

  • Length: 70.670 Km
  • Configuration: 4 lanes
  • Project Cost: Rs.  1357 Crs.
  • Client: Public Works Department, Govt. of Maharashtra

Consultancy Services for Detailed Plans and Estimates of incomplete and balance work of Sion - Panvel BOT Project.

  • Length: 23.09 kms
  • Configuration: 5+5 lane
  • Project Cost: Rs. 300 Crs
  • Client: PWD, Govt. of Maharashtra

DPR for 4/6 laning from MP – Maharashtra border to Dhule, Km 168/500 to Km 265/00, Section of NH-3 in the state of Maharashtra under NHDP Phase-III Programme (Package No. NHDP-III/DL4/06).

  • Length: 103.170 Km (Includes 5 bypasses, 3 Major bridges, 8 flyovers & 1 ROB)
  • Configuration: 4 / 6 lanes
  • Project Cost: Rs. 675  Crs.
  • Client: National Highways Authority of India, New Delhi

DPR for up-gradation of Umred - Bhisi - Chimur - Varora - Vani and Gondkhari - Kalmeshwar – Dhapewada - Saoner Section of NH-353E, 930E & 547E in the state of Maharashtra to two / four lane with paved shoulder configuration (Package No. - NH/IAHE/04).

  • Length: 150km (Includes 2 bypasses, 3 Major river bridges, 2 ROB’s, 8 Grade Separators)
  • Configuration: 2 / 4 lanes with paved shoulders configuration
  • Project Cost: Rs. 2040 Crs.
  • Client: NHAI, PIU, Nagpur

OTHER PROJECTS

  • DPR for up-gradation to Two Lanes with Paved Shoulder / Four lane configuration of Aurangabad – Vaijapur – Kopargaon – Shirdi (Section from Aurangabad – Lasur Station (MSH-12) and Vaijapur to Kopargaon (SH-65), New NH-752-I) in the State of Maharashtra (Package No. 08).

  • DPR for up-gradation of Two Lanes with paved shoulder / Four lane configuration of Parli – Ambejogai – Renapur (Latur Road), NH-548B in the State of Maharashtra.

  • DPR of selected state road stretches for 2 / 4 laning with paved shoulder NH Configuration under Bharat Mala Scheme – Pagal – Aladin K Bera – Berivanwala and Poogal – Barastpur – Ranjitpura – Charanwala – Naukh – Bap in the State of Rajasthan (Package No. 10).

  • DPR and Preparation of Land Plan by adopting LiDAR or similar technology for widening to two lane with paved shoulders for Package under Hybrid Annuity for
    • (a) Khambala – Telonda – Kasa – Talwada – Vikramgad – Pali Road
    • (b) Wada – Devgaon Road, SH 34 from Km 53/800 to 86/000
    • (c) Tembha – Khardi – Jawhar – Jamsar – Bopdari – Ruighar Road in the State of Maharashtra (Package No. MU-29).

  • DPR and Preparation of Land Plan by adopting LiDAR or similar technology for widening to two lane with paved shoulders for Package under Hybrid Annuity for
    • (a) Vaijapur – Gangapur – Bhendala – Dahegaon – Bidkin – Kachner – Karmad Road from Km 58/500 to Km 177/300
    • (b) Paithan – Pachod road (Package No. AU-53, Length -154 Km).

  • DPR for the work of Widening and Construction of MIDC Road from Taloja MIDC Road to Ambernath – Katai Naka Road in the State of Maharashtra.

  • DPR for widening of existing Aarey Road from WEH to L & T subway and construction of missing Link from Fim City Road to Aarey Road, Mumbai.

  • DPR for Rehabilitation and Upgrading to 2 Lane with paved shoulder configuration of the Heritage Route Ahmedabad – Dandi, NH-228, from Ahmedabad to Mahisar River (Excluding Mahi Bridge) in the State of Gujarat (Package No. DPR/DL-6/01).

  • DPR for Rehabilitation and Upgrading to 2 lane / 2 lane with paved shoulders configuration and strengthening of Lalsot to Dhoulpur section (Km 0 to Km 85 and Km 155 to Km 186) of NH-11B in the State of Rajasthan (Package No. SP/C/4).

  • DPR for Rehabilitation and Up-gradation to 2 lane with paved shoulders configuration of Biaora – MP / Rajasthan Border on NH-12 in the State of Madhya Pradesh (Package No. DPR/MP/02-09).

  • DPR for Rehabilitation and upgrading to 2 lane with paved shoulder configuration of Dhamtari to Jagdalpur (NH-43) in the State of Chhattisgarh.

  • DPR for the work of Integrated Road Development Programme (IRDP) for Sangli City in the State of Maharashtra.

  • Techno Feasibility Study for Construction of Mining Bypass Road in North Goa.

  • Techno Feasibility Study for Construction of Mining Bypass Road, Phase – III in South Goa.

  • DPR for Construction of Bypass from Porvorim to Baga Beach and from Calangute Church to Sinquerim in the State of Goa.

  • DPR for Construction of four lane road from Khandala to Jaigarh from Km 33/00 to 42/00 of part of SH 106 in the State of Maharashtra.
Scroll to Top